Friday, 27 November

GRIDCo restores 330kV Aboadze-Anwomaso transmission line damaged by illegal chainsaw operators

News
GRIDCo

The Ghana Grid Company Limited (GRIDCo) has completed repairs to the damaged 330kV Aboadze-Anwomaso transmission line, and it is back in operation.

In a statement issued in Tema on Thursday, November 26, 2026, the company said: "The Ghana Grid Company LTD. (GRIDCo) wishes to inform the general public that we have successfully completed repairs to the damaged 330kV Aboadze–Anwomaso transmission line, which has now been restored to operation."

According to the statement, "The transmission line was damaged on Wednesday, 25 November 2026, when a tree was felled onto it by illegal chainsaw operators."

GRIDCo said it then carried out the necessary repairs, which "were successfully completed on Thursday, 26 November 2026 around 12:07pm, with the damaged transmission line fully restored to operation."

The company appealed to the public "to help protect critical electricity transmission infrastructure by refraining from illegal chainsaw operations and other activities in the vicinity of transmission lines and associated facilities."

GRIDCo also thanked affected consumers, saying: "GRIDCo appreciates the patience, cooperation and understanding of all affected consumers during this period."

The statement was issued by the company's Corporate Communications Section.

Source: classfmonline.com